Initial
Contact
- This is where the request for electrical service is made.
-
+
Engineering
Response
- An Engineer will request paper plans and schedule the first site meeting with members from Engineering, Marketing, and Operations.
-
+
Initial
Contact
- While an Engineer designs the electric layout, Marketing will provide construction agreements, rates, deposits, and incentive programs.
-
+
Permit
& Design
- This is where the request for electrical service is made.
- The job is staked and the Engineering sends the project to Construction for scheduling.
-
+
Member
& Review
- The developer will review the design, final lighting layout, and cost estimate.
- The second site meeting can be scheduled here, and all paperwork should be complete for primary power.
-
-
+
Site
& Preparation
- The site should be at final grade and the right-of-way clear of all obstructions.
- GreyStone Power should be notified by the member once this is true.
-
-
-
+
Pre-Construction
Meeting
- This is the final site meeting before construction begins and will take place once locates and relevant inspections are completed by their respective organizations.
- Meeting should consist of members from Engineering and Operations.
-
Primary
Construction
+
- This is when construction takes place.
- The member will be notified upon completion and of the next steps.